killeen

The City of Killeen contracted with Pipeline Analysis, LLC to install thirty-five (35) temporary wastewater flow meters within the wastewater collection system to prioritize infiltration/inflow. This data was used by the City’s consultant to calibrate a hydraulic model of the system and prioritize the system for a phased rehabilitation program.

To date 4,579 manhole inspections (with rehabilitation recommendations), 277,230 linear feet of smoke testing and 41,600 linear feet of CCTV inspection has been performed.

Client: City of Killeen
Project Manager: James H. Forbes, Jr., P.E.
Owner Representative: Steve Kana, P.E.